Waukee Public Works Site Expansion Phase 1

Bid Date: 2PM on 12/09/2021

Scheduled Start Date

1/10/2022

Scheduled Completion Date

5/1/2023

A new 33,729 SF single story unheated public works equipment & salt storage building, located at 805 University Avenue, northwest of the existing building.

The building construction includes concrete slabs on grade, precast concrete walls, steel roof structures and adhered membrane roofs. Also included are fire protection, plumbing, mechanical and electrical work as well as site utilities, grading, and concrete paving.

The kinds of materials, estimated quantities, and work to be done for the project on which bids will be received are as shown on the bid proposal for said project. All work is to be done in strict compliance with the Plans and Specifications prepared by the Engineer which have been heretofore approved by the City Council and which are now on file for public examination in the office of the City Clerk.